Meplac (Liege) is specialises in manfacturing panels. The company manufactures its own internal doors without technical features. For functional internal doors, it calls on other suppliers.

Website: www.meplac.be

Assignment

  • 111 doors finished with an HPL finishing material in a specific colour.
  • Use of a special edge-strip with dovetail.
  • Lead time: less than three weeks after quotation. Three weeks after ordering the doors, the hotel was fully booked.

Problem

  • The average delivery time for such an assignment is 12 weeks. Moreover, just prior to the summer holidays, this delivery time can be even longer.
  • No supplier had sufficient HPL sheet material in the correct colour and structure available.

The client

“Last-minute orders are common during the weeks prior to the summer holidays, however this general contractor had waited a very long time to place his order”, states Christelle Mallegni, from the sales department. “Although the dimensions were standard and they did not have to satisfy other technical requirements, except those relating to the statutory fire resistance, it is still not certain whether, at the end of the working year, such new assignments will be ready on time. Moreover, the Hotel Eden has such a specific and exceptional decor, that the finish had to be extremely meticulous. For example, the colour of the HPL finishing material was dark grey and high-gloss, a colour that we did not have enough of in stock. For us, this assignment was simply a bridge too far. We certainly did not hesitate to summon assistance from Doorsolutions.”

Business Manager Christoph Baete from Doorsolutions

“I knew that the deadlines would be very tight, but you have to keep customers satisfied”, states Christoph Baete from Doorsolutions. “I therefore unconditionally committed myself in writing to meeting the deadline. We did not skimp on effort or expenditure in order to look for suitable cladding sheet material at suppliers throughout the whole of Belgium and France. Since no supplier could deliver the entire batch, we had to organise express transport to different companies. Moreover, since the dimensions of these panels were not the same, it was also a major puzzle to work out how all of the doors could be clad in a high-quality manner.”

Conclusion

Christoph Baete: “Via this assignment, we have demonstrated that we are able to successfully execute a project while standard time pressure, that under normal circumstances is also extremely time intensive, due to the steps that must be taken:

  • request
  • quotation
  • quotation amendment
  • prepare order
  • order confirmation
  • modification of order confirmation
  • order HPL and production planning
  • production
  • delivery with special express transport
Christelle Mallegni
Christelle Mallegni

Doorsolutions with the deadline exactly on time, and our customer was extremely pleased about the quality of the work as well as the delivery time. This once again demonstrated that Doorsolutions is a company that you can also depend on for assignments when under time pressure.

How we solve your door problems

We will be pleased to discuss a solution to your door problem without any obligation on your part.